Factory Direct Pricing Now Available - Contact Us Today for a Quote

Waste Water Coatings and Repair

Protect and repair your facility from hydrogen sulfide damage.

“Eco-Polymer is the one system that Provides Reliable Repair and Anti-corrosive Protection for Water-Wastewater Treatment Plants and in both wet or dry environments”

The Roger Road Wastewater Treatment Plant had an expensive problem; a severely deteriorated concrete splitter box needed to be repaired, but before any work on this operating structure could begin, a temporary but costly "pump around facility" had to be installed to handle the process performed by the splitter box, says John Munden, Civil engineering Manager with the Pima County Wastewater Management Department.

Contact us and receive your Novolac Free Epoxy Guide in 20 seconds!

Pima County Wastewater
Pre-job inspection: Severe Hydrogen Sulfide damage

Pima County North Wall
Notice the severe damage from the Hydrogen Sulfide


The splitter box is used to split the flow of raw sewage and direct it to various primary clarifier, he says. The structure was to have been part of a larger project to rehabilitate other concrete structure with a calcium aluminate cement under layment and epoxy topcoat, but the contractor handing that job declined to take on the splitter box, declaring that it couldn't be fixed, say Allen Kauffman, the president of another contracting firm that subsequently did the work using a polymer concrete repair product and an epoxy novolac lining.

Pima County - destroyed rebar
North chamber of splitter box: rebar had to be added to the area where 1 foot of cement and rebar was lost due to hydrogen sulfide/sulfuric acid

The covered splitter box is 8 ft wide, and 18ft long, and divided into two sections of different heights to aid in sewage separation. The turbulent contents of the splitter box encourage the development of hydrogen sulfide gas and the subsequent growth of microorganisms that attack the concrete substrate, says Kauffman. In addition, says Munden, the cover exacerbates the hydrogen sulfide problem by trapping the gas, increasing its concentration in the structure.

The deterioration of the splitter box was extensive, but not uniform, says Munden. In some areas affected by sulfuric acid attack, the concrete had lost over 50% of its original thickness. Concrete had been eaten away, exposing rebar. One wall, originally 12 in. (30.5 cm) thick, was reduced to a three-inch (7.6-centimeter) thickness, says Kauffman. The rebar in some areas had been completely corroded, he adds.

Given twelve days to do the work in November 2003, Kauffman’s company began the project by power washing the splitter box at 3,500 PSI (233 bar) to clean the concrete surface and remove loose material. The deteriorated areas were then abrasive blasted with copper slag. The contractor installed a new mat rebar system, securing it to concrete with drilled-in dowels or tying it to the existing rebar. The contractor then performed another power wash with an

fd

Applying polymer concrete repair material to primed wall in order to rebuild wall back to specifications

fd
Wall repaired to Original Specifications

Pima County repaired
Chamber after final lining application

injection of a soluble salt treatment. Blowers were set up, a five centimeter thick layer, says speed drying, and six hours later, the contractor began apply-Kauffman. The concrete repair material was allowed to setting the polymer concrete repair product by trowel. up for two hours before additional layers were applied.

Working on one wall section at a time, the contractor The contractor built the walls of the concrete structure applied the polymer concrete repair product. Back to their original thickness, in some cases taking a 1/8-inch-thick (3 mm) area back to 10 in. (25 cm). The contractor performed adhesion tests on the concrete repair product, noting that the cementation substrate failed before the polymer concrete repair product. The surface preparation, rebar installation, and rebuilding of the concrete took four days, says Kauffman.

Forced heat aided the cure of the concrete repair material, allowing the contractor to proceed with the lining application 12 hours later. Over two days, two coats of the chemical-resistant epoxy novolac lining were applied by brush and roller to a total thickness between 30 and 35 mils (750 and 875 micrometers). The epoxy novolac was heat cured over the first night and then heat cured for 24 hours following the final application , says Kauffman. According to Kauffman, Pima County had an inspector on site during all working hours.
The concrete splitter box rehabilitation was completed in less than 7 days, saving more money in “pump around facility” expenses than it cost to perform the work, says Kauffman. The contractor performed a follow - up inspection in March 2005, noting no signs of deterioration of the system. Munden says that, although a formal follow-up inspection has not been conducted on the operating splitter box, the lining system appears to be holding up well. He adds that the many of the metal components of the splitter box have been replaced and that it is slated for the installation of a ventilation system for odor control and hydrogen sulfide mitigation.

Novolac Epoxy Advantage:

Novolac Polymer

Click to Enlarge

Novolac technology is the cutting edge in epoxies.

We specialize in problem solving facility and utility issues.  

All of our Products are:

Valid HTML 4.01 TransitionalValid CSS!

 

Give us a call today (888) 858-3790 or email us and Speak one of our specialist for your free custom diagnosis for your project! (Product Data Sheets, MSDS sheets and Step by Step Surface Preparation Instructions available by request.)